A major programme of works to transform Mile End Library.
Phase 3 of the Mile End Library Transformation is well underway; starting in June, contractors have begun work to:
A book collection service is operating for items on the 1st floor, and there will be intermittent periods of noise affecting the 2nd floor north reading room. Due to work on the main staircase, there is scaffolding between ground, first and second floors reducing capacity, please take care when moving around these areas.
The work is scheduled to be completed in September, exact dates to be confirmed. You can find more information on the project, as well as progress photos on the Mile End Library Transformation Project webpages.